DTI Holding Point Metering and Regulator Station

Pike provided general construction services for Columbia Pipeline’s new interconnect station.

The approximate 2.6 area tract required the installation of a 200 MMSCFD M&R Natural Gas station connecting MPC to a 12” line A5 to DTI’s 30” LN-1 and DTI’s  26” LN-2. The new interconnect station was designed for single direction gas flow from MPC to DTI. The station piping was designed for 1200 PSIG MAOP. Scope of work included the installation of a filer separator and waste tank, meter skid, regulator skid, heater and opp value setting. Pike self -performed site work and concrete.

  • Location

    Horseheads, New York

  • Client

    Millennium Pipeline Company, LLC